Programme

The Churchmanor Estates Company plc and Morley Fund Management have worked hard to ensure rapid delivery of buildings for occupiers at Chesterford Research Park.

The experience of Building 900 demonstrates the speed of delivery that is possible at the Park.


· Initial Briefing - March 2003
· Terms agreed/solicitors instructed - May 2003
· Planning application submitted - May 2003
· Consent received - July 2003
· Start on site - September 2003
· Shell completion proposed - March 2004
· Tenant fit-out to occupation - October 2004

Occupiers have the comfort of knowing that Chesterford Research Park will deliver building solutions to meet their time requirements.

The programme can be quickened should an occupier's requirement be capable of being accommodated within the two existing planning consented buildings, that form part of the Phase One Buildings of the development.